Decided to replot for official pool but looking for help (if the feature is available) with PSChiaPlotter.
I’ve got a mix of drive sizes and i’ve got one job running which is replacing all plots on my 14tb drives. Easy done as they’re all 127 plot per drive (few are 128 but i’ll sort the ‘spares’ once done).
I’ve also got 8/12/16tb drives and want to que jobs for these as well. I’ve tested creating a new job for 8tb for example but once started it runs straight away along side the existing 14tb job which i don’t want as i’m using madmax integration.
Can you que jobs (job per drive size) so the next one kicks off once a full job is complete? eg, all 14tb drives finished replotting as per job ‘replot14’ then next job for next drive size, ‘replot8’ starts. etc etc.
Alternatively, has anyone got a ps plotmover script that will delete an existing plot from a drive directory before moving the new one over to the new directory? I’m moving final plots direct to final storage but this is soaking up 10min per plot for plot time in PSCP. If you can run a ps plotmover script that does this you could run native madmax, keep final plot on plot drive and have robocopy delete an old plot, copy over a new one and not have to think about different final drive sizing.
Current plotmover:
# Chia Plotting Automation Script
# by Kostya
<#
Simple robocopy command to move files from source to destination in a continious process
Modify as follows:
.\chia2drive.ps1 d:\ f:\ c:\scripts\filelog.log
#>
param (
[Parameter(Mandatory=$true)][string]$tempPath,
[Parameter(Mandatory=$true)][string]$plotPath,
[string]$log = "c:\log\chia2drive.log"
)
robocopy $tempPath $plotPath *.plot /J /MOV /MOT:10 /LOG+:$log /TEE